  • How do you make the Ready To Test column basically be the column for "Done" stories so that when the sprint is complete, the stories can be credited in the burndown and velocity reports?

How do you make the Ready To Test column basically be the column for "Done" stories so that when the sprint is complete, the stories can be credited in the burndown and velocity reports?

We need to give credit for velocity and burndown for stories that are in ready for testing. When ending a sprint, is there a way to give credit even though stories are not in the done column? 

1 answer

Yes, in your board configuration, go to the "Column" tab, you just have to specify on which Statuses/Column that the "Resolution" will be set where the issue is ultimately considered as close (resolution has a value).

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

36 views 0 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you