When any issues in Project A transition from status X to status Y, I would like to copy this issue to Project B with a different Issue Type. Both issues must be linked. The operation should be invisble to the user.

Is this possible? Any help muuch appreciated.

2 answers

1 accepted

2 votes
Answer accepted
JamieA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 12, 2012

You could use the Clone Issue function from the script runner plugin, this lets you specify a target project and issue type without writing any code.

Donncha Daly November 12, 2012

Thanks Jamie

0 votes
Bob Swift OSS (Bob Swift Atlassian Apps)
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 12, 2012

CLI Plugin for JIRA allows you to do various actions on transition.