How do I have JIRA display or report completed projects?

Will August 17, 2015

When projects complete they no longer display in the epic view.  How do I have JIRA display or report the completed projects? 

1 answer

1 accepted

0 votes
Answer accepted
Thiago Zandona
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 17, 2015

Hi Will,

For Scrum Boards you can use the Epics report, check here:

https://confluence.atlassian.com/display/AGILE/Viewing+the+Epic+Report

or better, you can use the Epic Work View for JIRA, it contains statistics on completed stories :

https://marketplace.atlassian.com/plugins/com.cobalt.jira.plugin.epic.EpicPlugin