How do I get useTFS to sync sub-tasks of stories, bugs and tasks?

Ivar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 11, 2014

Based on this issue, https://bitbucket.org/pigsty/usetfs/issue/59/unable-to-sync-both-task-and-sub-task, sub-tasks should sync just fine. But as I cannot find information about this in the wiki, https://bitbucket.org/pigsty/usetfs/wiki/Home, I am uncertain how I set this up to work properly for bi-directional sync?!

2 answers

1 accepted

1 vote
Answer accepted
Andrzej Pasterczyk
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 12, 2014

Hi Ivar,

https://bitbucket.org/pigsty/usetfs/wiki/Groovy%20expressionsTop level expressions - example 2

Ivar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 12, 2014
Andrzej Pasterczyk
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 12, 2014

Yes, somehow % sign was urlencoded when I did copy paste :)

Ivar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 18, 2014

@Andrzej, I still have some issues on this one. And the documentation is not that helpful:

- On the work item sync. config tool, there is a checkbox for "Try to sync parent/child..." Should this one be ticked off?

- Secondly, with this setting not used, TFS does not create any links for parent/sub-issues. This is quite frustrating.

Any idea?

0 votes
Ivar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 12, 2014

I have managed to get a sync on this now by specifying that Tasks in TFS <> Technical Tasks in Jira. This is not optimal however, so I will try and see if scripting will enable me to differentiate a Task on sub-level from a Task on parent-level.

Suggest an answer