Steven Behnke Community Champion Apr 27, 2015

If you use the Move function on a Sub-Issue, you can change the parent. The project is tied to the parent anyway.

image2015-4-27 17:2:56.pngimage2015-4-27 17:2:14.png

Thanks! I was trying to move it through the bulk edit method.  I didn't even know this Move menu was there.  So I learned something new smile

Steven Behnke Community Champion Apr 27, 2015

Cool! Glad I could help out! :) It's a little weird since Sub-Issues get their own options, you kinda just gotta know it's there :3

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,725 views 17 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you