Hi,
I am trying to import existing issues (stories, epics, bugs, etc.) from our JIRA systems.
At the moment, it seems that all the issues are imported with no estimations (story points).
In our JIRA the estimation exists.
Would anyone have a clue?
Cheers,
Guy
Hi,
Do the estimates show up in the import dialog where the issues to be imported are listed?
If yes: Is the option to keep the estimates checked in the bottom of that dialog?
If no: Could it be that the estimates are on a different (custom) field rather than the standard JIRA Agile points estimate field? Portfolio currently just considers the out-of-the-box issue fields, and no custom fields for the estimates.
If the estimates show up in the dialog, and the import option is ticket but estimates are still not imported, it's likely a bug and certainly not expected behavior. In that case, please raise a ticket via support.atlassian.com
Thanks,
Martin (PM for JIRA Portfolio)
image2015-1-30 15:44:15.png
What is the "out of the box" field for time estimate? I've tried Duration, Story Points, and Original Estimate (Time Tracking.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Martin,
You were spot on! It seems that we were using a custom field to capture story points.
We have fixed that now, and the import gets the story points as well.
Many thanks,
Guy.