How can i show the date of a subtask on parent level?

Hi,

I have the problem that my dashboard did not show the dates which ar included in my subtasks. So my question is, how can I create a filter with JQL which shows the date of the subtask field on parent level?

 

Please help.

Thank you very much and regards,

Daniel

1 answer

0 votes
Peter DeWitt Community Champion Sep 22, 2017

Daniel, it sounds like you need to be able to see all your subtasks as well as the parent issues on your dashboard.  

Scriptrunner adds the issuefunction in subtaskof() JQL function for pulling all subtasks of specific issues.  This is how I do it.

Hope this helps. 

-peter

Hi @Peter DeWitt,

Thanks for your answer.

Yes, but in my subtasks are dates and i would like to show them on dashboards. I have the problem that i can show the subtask on issuelevel, but my dates dont be showed. The space of my dates are empty. But when I create filters for my subtasks dates are going to be dispayed.

Do you know what I mean?

 

Thanks for help.

 

-Daniel

Peter DeWitt Community Champion Sep 28, 2017

Are the dates in your subtasks in a specific field?  Can you attach a screen shot?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

456 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you