I need to make that field mandatory because i wanna know how many time my team is dedicating to the ticket and make to them impossible to close the ticket a mark as solved without registering the time in the control time field
for anyone who is wondering what field it is, it is that in the figure. The language is in portuguese so the translation of ''control time'' must be wrong so a similar image should help
Go to the workflow used in that issue type and for the close transition add a validator "Field Required Validator" and then select "Time Spent" field.
Also make sure for the close transition there is a transition screen with the "Time Spent" field.
Ravi
hi @Ravi Sagar _Sparxsys_ , the workflow that i edited is marked as ''sketch'' it will work in the same way?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.