How can i get the time of subtasks to roll up to the top level task?

For example CX101 has 2 sub tasks

CX102 - of 4 hours

CX103 of 6 hours

I want CX101 to show 10 hours remaining. Is this possible?

Thanks

2 answers

1 accepted

0 votes
Accepted answer

Hello,

Time Tracking has an option of aggregating Sub-Tasks time as you can see at:

https://confluence.atlassian.com/display/JIRA051/Logging+Work+on+an+Issue

note that the summing of sub-tasks per story doesn't get calculated in a dashboard.

I'm using the Column gadget and selecting "Time Spent" and "Remaining Estimate"

Is this column gadget available for on demand users?

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,942 views 19 22
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you