I've started my sprint, but accidentally set the start date to a time in the future. Is there a way for me to go in after the sprint has started to change the start and end date?
Yes you can. Go to backlog -> active sprint.
You can edit the dates as in the image.
Looks like the option is no longer available. Can anyone advise how to change the start time of a Sprint? Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.