Hi,
I'm using the Plan view for our backlog.
There's the column where one can align "versions". Right now I have 1.4, 1.5 and 1.6 in there.
Unfortunately, 1.4 was entered later than the other two, and is now sorted beneath them in the list.
Can I change that somehow? I want 1.4 at the top.
Thanks,
I had the same issue. Somewhat surprisingly, this is not a setting on the Board Configuration (where you would expect).
What got me the result I was looking for was going to Project Administration --> <Project Name> --> Versions. I reordered the versions in reverse order to how I wanted them displayed in the Planning View.
This put the releases in a "less natural" (for me at least) on when I was performing a Release. However, since many more people use the Planning View than perform a Release, we went with it. HTH