Hi,

I'm using the Plan view for our backlog.

There's the column where one can align "versions". Right now I have 1.4, 1.5 and 1.6 in there.

Unfortunately, 1.4 was entered later than the other two, and is now sorted beneath them in the list.

Can I change that somehow? I want 1.4 at the top.

Thanks,

1 answer

I had the same issue.    Somewhat surprisingly, this is not a setting on the Board Configuration (where you would expect). 

What got me the result I was looking for was going to Project Administration --> <Project Name> --> Versions.  I reordered the versions in reverse order to how I wanted them displayed in the Planning View.

This put the releases in a "less natural" (for me at least) on when I was performing a Release.    However, since many more people use the Planning View than perform a Release, we went with it.  HTH

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,147 views 13 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot