Everytime I create a task, gets the status "to-do" but I need it in a custom one (ice box) is that possible to configure?
Thanks.
Assuming you mean JIRA, then yes.
Have a look at the "workflow scheme" for the project, which will tell you what workflows are in use.
Find the one for "task" and make a copy of it in the admin screens. Add the new ice-box status to it and change the "create" transition so it lands there instead of to-do
Go back to the workflow scheme and add the new workflow, and associate it with tasks.
Yes, sorry, JIRA!
Thanks for your quick answer, it works!
Best Regards!