How can I make sub-task to be displayed in th eBaclog section of the Scrum Board

Tal T. March 22, 2016
 

2 answers

2 votes
Michael Partyka
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 22, 2016

Hello Tal,

Actually, JIRA Agile will not count sub-tasks in. What I advise is to move them up one level. For instance, change issues to epics and sub-tasks to issues. This way you will be able to manage them in a more feasable way.

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 22, 2016

I'm afraid you can't.

The principle is simple - you don't need to rank subtasks, so you don't need to see them in the backlog.  They only matter within the context of their parent, so you can open that and see them there, but there's no need for them in the backlog.

Suggest an answer

Log in or Sign up to answer