How can I have a visual indication of how many days a subtask is in the status "In Progress" on the Scrum borad.

As a Scrum Master I want to have an indicator if a task is too long in progress. This is an every-day issue in a Scrum process.

1 answer

  1. Choose Configure from the Board dropdown menu
  2. Click Columns on the left hand side of the screen
  3. Check the Days in Column checkbox

You'll then see small dots on each subtask card showing how long they've been in the column their in. Hover over them to see an exact number of days. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

422 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you