I have a scrum board where time estimate are displayed in week/day/hour instead of hours, even though both the timesheet configuration (Administration > Add-ons > Timesheet Configuration) and the time tracking issue configuration (Administration > Issues > Time tracking) are properly set to Hours. How can I set my board to always display hours?
Edit: using JIRA Cloud v. 7.1.0-OD-05-006
From what i understood of your question i think you want to add a field to your layout. You can do that by going to your board, pressing the button "Board" up on the right and after on "Configure". In the left menu you can click on "Card layout" and add any field to that you need on the list. The field will be shown on the issues of your boards.
My question was about the sprint "Remaining" visible at the end of sprint in the Backlog view of a scrum board. It used to be displayed in hours (if everything is configured correctly) and now it shows the total in w/d/h. So this is not about card layout.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.