How can I display quarters or dates in Portfolio

Mark Montminy April 11, 2017

We're trying to create high level roadmap views of various projects using Portfolio. The one area we're struggling with is showing time frame reference in the timeline view.

While all the information for start / end etc is visible per initiative in the scope list, once condensed, say in the schedule report, so you can see how initiatives align with either months or quarters.

 

1 answer

0 votes
Roi Fine
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 25, 2017

Hi Mark,

Releases are Portfolio's refrence for time. You can use releases as milestones or quarters if you wish to view a time refrence on your schdule reports.

I hope that helps,

 