How can I disable the "Original estimate" and "Remaining estimate" fields against issue type?

I have 3 issue types and I only want to disable "Original estimate" and "Remaining estimate" fields in one issue type and not affect the other two. How can I do that?

2 answers

0 votes

Two options:

Change the "issue type screen scheme" so that one issue type uses screens with the "timetracking" field on it, and the other two use screens without it

Change the "field configuration scheme", having two "field configurations" - one with it hidden and one with it as it is now

Note that the first just hides the field in general, but it's still active in the background, so you'll still see estimates rolling up onto parents if you keep the estimates on subtasks etc.  The second method hides it completely.

Can you please elaborate the steps by steps of these two options? 

See https://confluence.atlassian.com/adminjiraserver071/project-screens-schemes-and-fields-802592517.html and read through "specifying field behaviour" and "defining a screen"

Can you please elaborate the steps by steps of these two options? 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

23,202 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you