How can I copy Original Estimate to Log Work if Log Work is empty

Hi

I need a way to copy Original Estimate to Log Work if Log Work is empty

Any suggestions?

Thanks

2 answers

This widget could not be displayed.

Hi Itamar,

You can do it using "Log work" post-function (provided by JIRA Workflow Toolbox) using the following configuration:

Captura de pantalla 2016-04-05 a las 13.09.26.png

Note that:

  • {00068} is field code for numerical value of field Original estimate (minutes).
  • {00025} is field code for numerical value of field Total time spent (minutes).

You will need to use the most recent version of JIRA Workflow Toolbox (2.2.9), since this version provides parameter Conditional execution. In case you can't update to that version, I can give you alternative solutions.

Regards,

Fidel

 

 

This widget could not be displayed.

Worked like a charm!!

Needed to change the  {00025} - 0 to {00025}=0

 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Friday in Jira

New 5k User Limit and Other Cloud Updates

Hi all! Lauren here from the Enterprise Cloud marketing team.  I have some exciting Cloud updates from #AtlassianSummit that I wanted to share. We want everyone in your organization to be ab...

119 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you