How can I calculate days in particular status (i.e."In progress") for all parents in sprint?

Evgeny Tylin August 31, 2017

Hi,

I want to know how much time spent each ticket in each column on board. Could you help me?

1 answer

0 votes
Andy Heinzer
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 1, 2017

JIRA does not handle this particularly well, but there is a KB that explains what options are available for this:

Tracking the time taken for each workflow transition

From that page there mention of the JIRA charts, but this really only shows the average time, not the specific time for each issue.

If you're looking for more specific info on each issue:


The JIRA Suite Utilties plugin adds this functionality to JIRA.

The Time in Status plugin also can provide this functionality in JIRA.

Evgeny Tylin September 4, 2017

Thanks Andy