I have a plan that includes 8 teams and their boards as well as a couple of other sources. The plan is slow when set up this way, seemingly due to the large amount of sub-tasks and historical issues included in the teams' board filters.
I need to be able to do both of these at the same time:
1) base the plan on more restrictive queries like
project = TEAMX and IssueType != sub-task and (resolutiondate is null or resolutiondate > startOfYear())
2) associate the Portfolio teams to the correct boards so I can see sprints in my plan, plus the team velocity history.
I was able to write per-team JQL filters and at least link the teams to those, but it doesn't solve #2, making the teams useless.
I raised a sgguestion at https://jira.atlassian.com/browse/JPOCLOUD-1992.
Any ideas?