How can I base a portfolio plan on team boards without including sub-tasks?

I have a plan that includes 8 teams and their boards as well as a couple of other sources.  The plan is slow when set up this way, seemingly due to the large amount of sub-tasks and historical issues included in the teams' board filters.

I need to be able to do both of these at the same time:

1) base the plan on more restrictive queries like 

project = TEAMX and IssueType != sub-task and (resolutiondate is null or resolutiondate > startOfYear())

2) associate the Portfolio teams to the correct boards so I can see sprints in my plan, plus the team velocity history.

I was able to write per-team JQL filters and at least link the teams to those, but it doesn't solve #2, making the teams useless.

I raised a sgguestion at https://jira.atlassian.com/browse/JPOCLOUD-1992.

Any ideas?  

0 answers

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Thursday in Jira

Continuous visibility with the new Jira Software Cloud and Bitbucket Cloud integration

Hey Atlassian community, I am a PM on the Bitbucket Cloud team and I am excited to share that we just released an improvement to the Jira Software and Bitbucket Cloud integration. With the newly im...

148 views 0 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you