How can I assign cost/price per unit/hour to a task/resource

datasecmx January 13, 2018

Hello community, can you please help me with a simple question...?

How can I assign resources, and then cost/price per resource, task, worked time, etc?

2 answers

2 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 14, 2018

You need a resourcing add-on such as Tempo budgets

1 vote
Steve Thornhill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 14, 2018

Have you looked at Tempo or Portfolio to add the extra features?

datasecmx January 14, 2018

Do you have the link for portfolio add on so I don’t confuse with other ?

Steve Thornhill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 14, 2018

https://www.atlassian.com/software/jira/portfolio

 

But as Nic mentioned, the Tempo tools will give you more around the type of resource allocation you are looking for. 

https://tempo.io/

Suggest an answer

Log in or Sign up to answer