How can I add +/- 20% variance lines to the forecasted trendline on my burndown chart?

I am using Greenhopper to create burndown charts for my team.  The burndown chart depicts our forecasted trendline well.  I would like to add a "+20% variance" and a "-20% variance" line above and below, respectively, my forecasted trendline.  These lines are intended to depict our acceptable level of variance in the burndown. 

Is it possible to add such a line?

1 answer

1 accepted

0 vote
Timothy Chin Community Champion Oct 15, 2014

Unless you write your own add on module using the data from JIRA Agile, that is not an option at the moment.

I figured that that was the case. I'm pretty familiar with Jira and these burndown charts and I haven't seen anything like what I'm requesting in the question above. Wanted to check with the community to make sure. Thanks for the input!

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

212 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you