How are these calculations made in JIRA Portfolio?

steve tolson June 1, 2015

How are these calculations made in Portfolio: % complete, progress, free capacity, planned capactiy, and capacity utilization?

2 answers

1 accepted

0 votes
Answer accepted
Martin Suntinger
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 8, 2015

Hi Steve, 

See https://confluence.atlassian.com/display/JIRAPortfolioServer/Status+and+Progress+Tracking for how progress (%complete is aggregated with different progress tracking options available) 

At the very bottom of this page, there is an overview on the capacity view: https://confluence.atlassian.com/display/JIRAPortfolioServer/The+Graphical+Schedule 

Generally, free capacity in a time period is calculated by adding up the weekly hours of all available team members, or in case of planning in story points, simply the velocity forecasted for a particular sprint. 

Planned capacity is the sum estimates in JIRA Portfolio of work items scheduled into a particular time period, putting these two in relation (planned/capacity) gives the utilization. 

Cheers, Martin

0 votes
S__Ali_Nawab July 2, 2015

"Generally, free capacity in a time period is calculated by adding up the weekly hours of all available team members, or in case of planning in story points, simply the velocity forecasted for a particular sprint."

How does JIRA portfolio forecast the velocity for a particular sprint and what is the formula to determine this value?