How are average velocities calculated for the Version Report

When working with multiple scrum teams on a software version how is the average velocity calculated?  If story point estimation varies widely across the teams is there any way to account for this?

2 answers

0 votes
Justin Burke Atlassian Team Jan 13, 2015

Hi Tom,  

Here is some documentation that you may want to check out:  https://confluence.atlassian.com/display/AGILE/Velocity

 

 

Hi Justin, thanks for the link.

I was wondering how things are done when you have multiple scrum teams working on the same project.  The story point estimates vary considerably among the teams so how are velocity averages calculated in this situation?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

465 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you