For JIRA Agile Burndown in v7.1.9

Cinthy Janse June 12, 2017

Could someone please help us clarify a few things?

1) If we are using a customized worfklow and therefore, added additional columns to match this workflow. Does the burndown chart only look at the right-most (last column - "Done") and as long as the resolution is set to something will it see it as completed?

2) Some users are having issues  with showing "Remaining Time Estimate". We can see it as an active option on the list, but it won't select. Under Estimation for the board, "Original Time Estimate" was selected for Estimation Statistic, and "Remaining Estimate and Time Spent" was selected for Time Tracking.

3) We have some users that are when we're doing doing a burndown, the red line (actual progress) is flat. We're expecting that it should go down as issues are completed since we are measuring Remaining Time Estimate

 

Thanks

 

2 answers

0 votes
Cinthy Janse June 13, 2017

Hi Nic,

Thanks for helping us with this. Greatly appreciate it!

For issue #2, when selecting "Remaining Estimate" from the list. We can select it, but then it doesn't "hold" it...it'll refer back to the option it had previously (eg. Story Point).  The board configured under Estimation  has "Original Time Estimate" was selected for Estimation Statistic, and "Remaining Estimate and Time Spent" was selected for Time Tracking. Did we miss anything in the configuration?

burndown chart axis.jpg

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 12, 2017

1) Yes, that's pretty much it - the right-hand column matters.

2) I don't understand what "it won't select" means.  The settings on the rest of it seem good, I just don't grasp the problem

3) Are the issues they complete a) being put in the far-right column, and b) having time estimates?

 

Cinthy Janse June 13, 2017

 

Hi Nic,

Thanks for helping us with this. Greatly appreciate it!

For issue #2, when selecting "Remaining Estimate" from the list. We can select it, but then it doesn't "hold" it...it'll refer back to the option it had previously (eg. Story Point).  The board configured under Estimation  has "Original Time Estimate" was selected for Estimation Statistic, and "Remaining Estimate and Time Spent" was selected for Time Tracking. Did we miss anything in the configuration?

burndown chart axis.jpg

Cinthy Janse June 13, 2017

For #3, Is the "Remaining Time Estimate" based on the manual and/or calculated (using the log work) entry?