For JIRA Agile Burndown in v7.1.9

Could someone please help us clarify a few things?

1) If we are using a customized worfklow and therefore, added additional columns to match this workflow. Does the burndown chart only look at the right-most (last column - "Done") and as long as the resolution is set to something will it see it as completed?

2) Some users are having issues  with showing "Remaining Time Estimate". We can see it as an active option on the list, but it won't select. Under Estimation for the board, "Original Time Estimate" was selected for Estimation Statistic, and "Remaining Estimate and Time Spent" was selected for Time Tracking.

3) We have some users that are when we're doing doing a burndown, the red line (actual progress) is flat. We're expecting that it should go down as issues are completed since we are measuring Remaining Time Estimate

 

Thanks

 

2 answers

This widget could not be displayed.

1) Yes, that's pretty much it - the right-hand column matters.

2) I don't understand what "it won't select" means.  The settings on the rest of it seem good, I just don't grasp the problem

3) Are the issues they complete a) being put in the far-right column, and b) having time estimates?

 

 

Hi Nic,

Thanks for helping us with this. Greatly appreciate it!

For issue #2, when selecting "Remaining Estimate" from the list. We can select it, but then it doesn't "hold" it...it'll refer back to the option it had previously (eg. Story Point).  The board configured under Estimation  has "Original Time Estimate" was selected for Estimation Statistic, and "Remaining Estimate and Time Spent" was selected for Time Tracking. Did we miss anything in the configuration?

burndown chart axis.jpg

For #3, Is the "Remaining Time Estimate" based on the manual and/or calculated (using the log work) entry?

This widget could not be displayed.

Hi Nic,

Thanks for helping us with this. Greatly appreciate it!

For issue #2, when selecting "Remaining Estimate" from the list. We can select it, but then it doesn't "hold" it...it'll refer back to the option it had previously (eg. Story Point).  The board configured under Estimation  has "Original Time Estimate" was selected for Estimation Statistic, and "Remaining Estimate and Time Spent" was selected for Time Tracking. Did we miss anything in the configuration?

burndown chart axis.jpg

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Aug 06, 2018 in Jira Service Desk

A is for Activate: Share your top Jira Service Desk onboarding tips for new users!

Hi, everyone! Molly here from the Jira Service Desk Product Marketing Team :).  In the spirit of this month's  august-challenge, we're sourcing stories of Jira Service Desk activation fro...

576 views 25 15
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you