Fix dates in Portfolio for Jira

Hey there!

The last days I am testing Portfolio for JIRA! It's an awesome tool and I like it very much!

But I have ONE question: How can I create entries with an fix date?

For example: Meetings in a project process only can be on Wednesdays, for Projekt A only at 18.1., 25.1. and 1.2.

The scheduled start is not enabled!

image2017-1-24 8:39:29.png

 

So do you have any solutions for me?

Thank you!

Christian

 

1 answer

0 votes

Hello,
You can define the earliest start date and the target start.
I believe you will find everything you need on this page, under the section Earliest start date.

Cheers,

 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,614 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you