Filter Timesheet by date

patrecialj January 23, 2020

Hello,

 

Is there a way for us to filter the timesheet by date.

 

Example: I want to see the Time Spent on the Project for Jan 1 to Jan 5 only.

 

Thank You

 

1 answer

0 votes
Adria Alonso
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 24, 2020

Hello Patrecialj,

You can make see it on Calendar if its a short period.

You can also get the issues of thos days in adv.Search JQL

worklogDate > '2020/01/01' AND worklogDate < '2020/01/05' AND project in (XXXXX)

XXXXX projectID

I hope it helps