Facing issue in Sprint planning

Ashwin Kupatkar June 26, 2016

Hi,

There's a situation. I added 10 issues with estimates to a sprint for sprint planning. But i released that i want to remove 3 issue from the sprint and put it in the next sprint. 

So now i am left with 7 total issues to be worked with in the Sprint, but then i decided to added new 2 issues and my total issues to be worked in the sprint changes to 9 issues.

But the pain in the butt is that i am not getting rid of the estimates planned for the issues' (3 issues) which i removed from the sprint and hence i am getting wrong sprint report.

Need help.

Regards,

Ashwin

2 answers

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 26, 2016

If you've started a sprint, then this is doing the right thing - moving issues in and out of an active sprint is scope change, so it's recording it.  You should avoid doing that, as it messes up what you've planned.

0 votes
Ashwin Kupatkar June 26, 2016

Thanks Nic smile

Suggest an answer

Log in or Sign up to answer