Estimates on Story & Subtask

Hi,

My question is:

1)Initially we give ball park estimate of effort in hours  to a story if i dont want to go with a storypoint.The Orginial estimate graph also appears

2) Now at the subtask level ,we get more granularity and add subtask and login the hours required.

In this case now the subtasks hours also get added to a story .Is this not an issue?

1 answer

Hi Jacob,

In the Story page, in the box with the estimates, you can uncheck the "Include sub-tasks". This way, you will only see the hours of the Story, not its subtasks. Obviously, you won't see the hours logged in the sub-tasks.

Alternatively, you can enter estimates in your Stories, not in the sub-tasks, and log hours in the sub-tasks. You will see the Original Estimate and the time logged. However, the remaining estimate won't go down when you log time.

Hope this helps

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Wednesday in Jira

Join our webinar: How 1B+ feature flag events helped us build the new Jira

Every time you release software, there's a bit of risk – that there's a bug, that something breaks, or that the feature doesn't resonate with customers. Feature flagging helps make high stakes s...

134 views 0 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you