'Estimates' of my stories in Portfolio does not change when I assign story points in backlog?

Hi,

If I, in the backlog, change my story points, this is not updated in Portfolio, estimates does not change?

Is that possible?

 

THanks,

 

Jeroen

1 answer

Hi, Jeroen! 

There's a great thread about this problem here: https://community.atlassian.com/t5/Jira-questions/Story-points-are-not-synchronized-in-Portfolio/qaq-p/189113/jump-to/first-unread-message

If that does not apply to you, there are a few other things that could be happening. 

If the Story is Resolved or Closed, the Plan won't update the estimate. If you've changed the Story Points field on the Epic, it won't update. Portfolio does not recognize changes to the field on that issue type (this has been the behavior since 1.x).

If you're changing it on the Story, and looking for it in the Plan, clicking the calculate button should pull that estimate in (provided the above things are false). 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira Service Desk

How the Telegram Integration for Jira helps Sergey's team take their support efficiency to the bank

...+ reading Fantasy). The same is true for him at the bank he works for: Efficiency is key when time literally equals money. Read on to learn how Sergey makes most of the time he has by...

340 views 2 4
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you