Estimate for subtasks

Michael Kuhl June 22, 2016

I'm evaluating JIRA. I have created an issue with subtask. For the issue I can enter an estimate value but I have no fields where I can enter an estimate value for the subtasks.

When I try to start a sprint, I get a warnung "Issues xxx and yyy do not have a value for the 'Estimate' field. Values entered after the start of the sprint will be treated as scope change."

I have setup "Estimation Statistic" to "Original Tine Estimate".

PS: Version 7.1.7

 

 

1 answer

1 vote
Elifcan Cakmak
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 22, 2016

hi,

you can add timetracking field to the create screen of your subtask screen scheme. that way you can enter original estimate value for the subtask too. 

Suggest an answer