I'm evaluating JIRA. I have created an issue with subtask. For the issue I can enter an estimate value but I have no fields where I can enter an estimate value for the subtasks.
When I try to start a sprint, I get a warnung "Issues xxx and yyy do not have a value for the 'Estimate' field. Values entered after the start of the sprint will be treated as scope change."
I have setup "Estimation Statistic" to "Original Tine Estimate".
PS: Version 7.1.7
hi,
you can add timetracking field to the create screen of your subtask screen scheme. that way you can enter original estimate value for the subtask too.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.