Estimate for subtasks

I'm evaluating JIRA. I have created an issue with subtask. For the issue I can enter an estimate value but I have no fields where I can enter an estimate value for the subtasks.

When I try to start a sprint, I get a warnung "Issues xxx and yyy do not have a value for the 'Estimate' field. Values entered after the start of the sprint will be treated as scope change."

I have setup "Estimation Statistic" to "Original Tine Estimate".

PS: Version 7.1.7

 

 

1 answer

hi,

you can add timetracking field to the create screen of your subtask screen scheme. that way you can enter original estimate value for the subtask too. 

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,788 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot