Estimate and Actual Hours

Marthi Lokanadh September 6, 2016

This question is in reference to Atlassian Documentation: Creating an Issue

I have created scrum development project. while creating new Issue which does not shows Original Estimate and Remaining Estimate options. Could you please let me know why these options are not displaying and where I can change settings

1 answer

0 votes
Peter Geshev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 6, 2016

Hi Marthi,

Maybe the fields are not visible on the Create Issue screen and you will have to add them manually. For more info on screens and fields see the documentation.(see the Configuring a screen's tabs and fields section)

Regards,

Peter

Suggest an answer