You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
I created Epic in different project and Stories in different projects and then link the epic to these stories.
But i am not able to see epic burndown. I think, epic burndown chart will take the stories/tasks that are in the same project as in epic.
What should we do to show epic burn down chart with the stories/tasks created in different project.
Hi @Madakannu Prabhu and welcome to the Community!
Charts - such as the burndown chart - are linked to a board and not a project. If you create a board based on the data coming from the multiple projects, I would suspect the reports should look fine too.
Your board filter (accessible from board settings > General) should fetch all your epics, as well as the issues from other projects.
Hope this helps!