Ended Sprint - Velocity Report not updated?!

Marla Landolt January 25, 2014

Issue: Ended Sprint5 -> Velocity Report shows 0 committed/0 done for ended sprint? In Plan-mode there were 73.5 SP completed, '0' at work; '5' not started just before I just ended the Sprint.

What did I do wrong? How can I correct this? We worked very hard. We need a running velocity report is not broken.

Help! I need to display the velocity report the day after tomorrow to shareholders.

See velocity report for Sprint5:

See burndown chart sprint5:

many thanks in advance for QUICK support! :-)

1 answer

0 votes
JanaW
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 13, 2016

Did you ever get this resolved? I just had an issue where I started a sprint and it shows no issues committed and I can't figure out why.

Suggest an answer