Duplicate subtasks for different epics

I have around 16 epics that will all require the same subtasks created for each epic. Is there any way I could clone a batch of subtasks and assign them to a new epic. I have around 30 subtasks and if I need to manually do the subtasks for each, my hair will go white before I finish.

1 answer

Easiest why I can suggest is to set-up the 1st EPIC/Subtask set and then clone it, keeping the subtasks. You can then make mods to the new (cloned) EPIC.

I might wonder why you have subtasks attached to the EPIC instead of stories, but it's all about how you want to do things! wink

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

172 views 1 17
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you