Done Issues in Sprint

We have a project which is taking a number of sprints before items are ready for release. So lots of issues/stories are sitting in UAT. We have mapped our columns so that the workflow DONE appears in ready for UAT. But these stories keep rolling over into the next sprint.

Any idea what I need to do so that they don't get rolled over when we create our new sprint?

2 answers

1 accepted

0 votes
Accepted answer

So we have had to create a number of different boards... it's all very confusing now.

Hi Frances,

It might be helpful to create 2 different boards for your project: 1 for the development team with only development items (going from to-do to done) and 1 to get an overall view on the process, with al the statuses from original idea over development to release.

You'll still be able to monitor the whole process and the dev team will have a better focus with only the relevant information for them to be shown.

Could this be a solution for your problem?

Kind regards,

Tom

Yeah - we have tried that, the problem is when we do reporting, the items are still showing as rolling over into each sprint whcih gives a skewed view of what has been done.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,097 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you