Does Portfolio have a separate database from Jira?

Janet Lunde March 27, 2015

The instructions say to import the issues, which implies that, but it seems puzzling.

How do you keep JIRA and Portfolio in sych? See progress on projects in Portfolio while planning?

 

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 27, 2015

Sort of, yes. It is a not a separate database but the data is not in JIRA as "issues".

Regarding the syncing question, refer to Martin's answer on https://answers.atlassian.com/questions/11985740

Also see, https://confluence.atlassian.com/display/JIRAPortfolioCloud/Synchronization+Settings and https://confluence.atlassian.com/display/JIRAPortfolioCloud/Regular+Plan+Updates