Hello,

I have a number of boards created in the same project, and when selecting them while configuring Sprint burndown gadget, i get hours or story point in the y-axis.

What triggers the sprint burndown to display hours or SP? Can I overrule this somehow?

 

 

1 answer

1 accepted

0 votes
Answer accepted
Jack Community Leader Oct 11, 2019

this is controlled by your choice of Time Estimation for the board in question. Go to the board settings and Estimation and choose Original Time Estimate for hours.

Thanks Jack. This is useful.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted in Jira

Demo Den Ep. 7: New Jira Cloud Reports

Learn how to use two new reports for next-gen projects in Jira Cloud:  Cumulative flow diagram and Sprint burndown chart. Ivan Teong, Product Manager, Jira Software, demos the Cumulative ...

303 views 1 3
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you