Depending the board the sprint burndown gadget has different y-axis (SP vs h)

Hans.meijer October 11, 2019

Hello,

I have a number of boards created in the same project, and when selecting them while configuring Sprint burndown gadget, i get hours or story point in the y-axis.

What triggers the sprint burndown to display hours or SP? Can I overrule this somehow?

 

 

1 answer

1 accepted

0 votes
Answer accepted
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 11, 2019

this is controlled by your choice of Time Estimation for the board in question. Go to the board settings and Estimation and choose Original Time Estimate for hours.

Hans.meijer October 11, 2019

Thanks Jack. This is useful.