How can I customize the workdays using the Greenhopper Classic Days Remaining gadget? My team is working 6 days a week, but the gadget only accounts for M, T, W, R, F.

Need it to be customized to M, T, W, R, F, S.

2 answers

0 votes
J. Alan Goddard August 13, 2013

Thanks Pietro. I should have mentioned that I am used GH for JIRA OnDemand.

When I open the Cofiguration page, I do not have an option to modify "working days". I only have the option to add "Non-Working Days"

By using OnDemand make a difference?

Thanks -

J Alan

0 votes
pschaff01
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 13, 2013

Hi there,

Inside the GH board, you can click on "Configure"(inside the cog icon on the top right of the screen) and then modify the "Working Days" to include Saturday. This will automatically refresh the days remaining counter to the correct value (including the additional saturdays).

Regards,

Pietro Schaff

J. Alan Goddard August 13, 2013

Thanks Pietro. I should have mentioned that I am used GH for JIRA OnDemand.

When I open the Configuration page, I do not have an option to modify "working days". I only have the option to add "Non-Working Days"

Does using OnDemand make a difference?

Thanks -

J Alan

J. Alan Goddard August 13, 2013

I ended up having to go into Time Tracker and change the number of work days to 7. This fixed the problem.

Suggest an answer

Log in or Sign up to answer