Create New Plan: Team Only Assigned to Issues with a Sprint

Matthew Leach January 8, 2018

When I created a brand new plan and used the default pre-created teams, I noticed teams were only assigned to an issue if it was already to a sprint. Is this expected behavior? I thought it was strange only certain issues were assigned to teams. I used a one to one mapping of board to team so thought every issue would be populated with the team. 

1 answer

1 vote
Cameron Eldridge January 9, 2018

Hi Matthew,

Teams are also suggested when issues have estimates (story points or remaining hours/days) applied to them. Do your issues in question have estimates? If not, no team will be suggested. This is a Portfolio calculated suggestion, which is indicated by the light blue background behind the text. If you explicitly designate a team to work on an issue, the background behind the Team will be white.

Best,

Cameron