Copy from field to another - how to?

Hi Everyone,

we made an error while importing a project from Bugzilla to JIRA: we copied version values to Affect's version field instead of Fix version field.

Is it possible to copy all values from Affect's version to Fix version for all issues?

Thanks,

Rumi

1 answer

1 accepted

0 votes
Accepted answer

Easy thing will be to do a bulk edit. But if you already have some value in fixVersion field, bulk edit will over write it and so you might want to do the fix in database.

Hi Jobin, the idea is good but we have different values for almost each issues. So we should do bulk edit 1000+ times, right? Or you know a trick? Thanks

I wouldn't do bulk edit then. Fixing in database would be easier.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,767 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you