Concurrent build limit

Chaikou Balde May 20, 2013

What to do when trying to build manually a plan and this tool tip appears: "Plan cannot currently be run because you have reached your concurrent build limit"? The build is shown as queued in jira

1 answer

1 vote
Harry Chan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 21, 2013

Hi, check the number of concurrent builds that has been set for your instance https://confluence.atlassian.com/display/BAMBOO/Configuring+concurrent+builds

If you reach that limit it'd be queued. Do note that if you enable too many, there could be performance issues.