Completing a Sprint Edited

I completed a Sprint 1 I created in the Cloud Trial Version of the Jira Product and I'm having a problem Starting Sprint 2?  Need help? Thxs.

 

 Jira2.jpg

2 answers

0 votes

When you say "completed", you mean you have put the end date on it and closed it?

Could you give us a wider/longer screenshot, showing the headers of both sprints?

Issue with the horizontal scroll bar. End date is displayed. I might have figure out the problem? I created a 2 week Sprint, but complete the Sprint I day instead of scheduling the sprint over a twp week span. Thoughts?Jira3.jpg

That looks like an open sprint to me.  Where's the header of the next sprint?

I located the sprint Complete button!

I've been creating and completing sprints and select dates a created 2 week sprints. The List of sprints I completed are not being displayed at the bottom of the burnbown chart. Only one sprint at a time. 

Does Jira provide burnup charts?

 

 

 

Ah, good.

There's no burnup built in to the off-the-shelf system, but a few add-ons provide one.

got it!

Troubled? I created several Sprints and completed each Sprint idividually, of course. The Sprints trail each other by 2 weeks

ie. Sprint 1- 5/29/2017 to 6/12/2017 Sprint 2 - 6/13/2017 to 6/27/2017 Sprint 3 - 6/28/2017 to 07/12/2017 and so on...

The Burndown Chart doesn't display the Sprints in a consecutive order, I only see Sprint 1?

thxs Larry

 

There's a drop-down to select the sprint in the chart.

got it - thxs

 

Nic,

Creating a "Critical" filter and I recieve the following error message below? 

Also, I assigned an estimate (ie 6 pts) to an issue. when I changed the issue to a Tasks or Bug and I lose the estimate? 

Jira5.jpgAlso, I assigned an estimate (ie 6 pts) to an issue. when I changed the issue to a Tasks or Bug and I lose the estimate? 

 

That error means what it says.  Your pririty list does not have "Critical" as an option.

You will lose an estimate if the field does not exist for the issue type you are changing to.  JIRA will warn you about data loss during the move.  However, it won't tell you if you move to a type where the field exists, but is not shown.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

27,263 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you