We have a self-hosted JIRA instance.
I've noticed that every time a sprint is closed and new one is created, many tasks (US/bugs) are moved to the new sprint, even if their status is "CLOSED".
What are we doing wrong? How to get rid of those annoying forever-alive tasks?
Hi Jakub,
do you have the Closed-state as last (= most right) column on your task board?
Issues that are not in the most right column of the board are moved to the next sprint.
When I click "View Workflow" next to "CLOSED", it displays a graph like this...
So I guess only "ACCEPTED" tasks are considered truly finished, right?
Is it possible to have both "ACCEPTED" and "CLOSED" as terminal states? (I don't admin the JIRA, I don't really know all of those things)