When i complete an issue, i move it to "Resolved". Is it possible to have it automatically move to "Done" after X amount of time (like 5 days or something like that)?
Set up the workflow to have a "resolve -> Done" transition, then write a filter that says "status = resolved < -5d", then use a jelly escalation script to trigger the close transition.
See https://confluence.atlassian.com/display/JIRA/Jelly+Escalation
Please refer the following link - it explain how you can do this.
https://answers.atlassian.com/questions/129807/automatic-change-in-transitions-status-in-jira-workflow.