Hello ,

 We have  5 sprints ,sprint 1 to sprint 5 .  presently we are in sprint 4 . i closed all the sprints sprint 1 ,sprint 2, sprint 3.    when we are cloning the tickets in sprint 4 ,   sprint 2 also automatically updating . is there any reson behind this ?

Thank you 

2 answers

0 votes
Thomas Schlegel Community Champion Aug 16, 2017

Hi Vidhya,

if you clone an issue, you decide, if the the sprint values should also be cloned:

image.png

If you check "Clone sprint values" - the clone will also be added to your old sprints.

Hello Thomas, 

 

I dont have that options like clone sprint values , clone sub-tasks , clone attachment. 

 

what should i do old sprints i.e closed sprints  not to be assigned to present sprint status  tickets? 

 

Thank you

Thomas Schlegel Community Champion Aug 16, 2017

what do you see, if you click on "Clone Issue" ?

image.png

Hello Thomas, 

 

i dont have options like your system . Please see image Capture.PNG

Thomas Schlegel Community Champion Aug 16, 2017

Do you try to clone an issue with Sprint values?

I've tested this also in my cloud testing environment and there I also get this field, if an issue has a sprint value:

image.png

If the issue has no sprint value, the field is not visible - as it is in your screenshot.

Yes Thomas, i tried to clone an issue with sprint values . That time also  not showing that 3 options.

Thomas Schlegel Community Champion Aug 16, 2017

that's strange... which version of Jira do you have?

Thomas Schlegel Community Champion Aug 16, 2017

that is the problem - this function was introduced in version 7.2

oh.. then what should i do now ? is there any other solution to hide the  closed sprints in the present sprint tickets ?

Thomas Schlegel Community Champion Aug 16, 2017

no, I don't know any easy solution for your Jira version. You can reopen a sprint and remove the cloned issue from the sprint. After that close the sprint again.

Or update your Jira server, which might be the better solution in the longer term.

Thank  you Thomas ,  will check 

Thomas Schlegel Community Champion Aug 16, 2017

You're welcome, Vidhya.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,541 views 15 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you